How long does the build process take

5-8 weeks on average. It all depends upon the complexity of the design..


Question-Mark-Logo.png

WHAT IS THE PRICE OF A BASE POOL AND WHAT DOES IT INCLUDE

See pricing and pool packages here.


Question-Mark-Logo.png

WHAT IS THE PAYMENT PROCESS THROUGH YOUR COMPANY

5 payments collected throughout the construction process:

  1. After dig

  2. After plumbing & steel

  3. After gunite

  4. After deck

  5. After interior


Question-Mark-Logo.png

How does Signature Pools & Spa communicate with homeowners during construction

Customer service will call or text at the end of each week to inform you of the tentative schedule for the following week. This is construction so flexibility is required. Additionally, you will receive Pentair SMS / Email notifications pertaining to schedule, inspections, color selections, payments, and homeowner duties throughout the build.


Question-Mark-Logo.png

ONCE THE POOL HAS STARTED FILLING, WHAT DO I NEED TO DO

Continue filling until the water level reaches the middle of the tile. It is important to not shut off the hose until the water level is at specified height.


Question-Mark-Logo.png

DO I NEED TO BE HOME FOR CITY OR COUNTY INSPECTIONS

Varies by location. City of Clovis and Fresno only requires you be present for 3rd and final inspection.


Question-Mark-Logo.png

ONCE THE POOL HAS BEEN FILLED, HOW SOON CAN WE SWIM

Immediately.


Question-Mark-Logo.png

HOW LONG SHOULD I STAY OFF NEWLY POURED CONCRETE

A minimum of 2 days to allow concrete to cure properly.


Question-Mark-Logo.png

AFTER PLASTER / PEBBLE, CAN I WALK IN THE POOL BEFORE FILLING WITH WATER

No. Not until the pool has completely filled with water. Otherwise, you run the risk of staining the interior.